Five Strategies to Streamline Construction


Through this article, Keith Simpson outlines essential strategies to mitigate common construction delays and enhance project efficiency. Drawing on over two decades of experience, Simpson emphasizes the importance of thorough site civil due diligence to address potential issues before construction begins. He offers actionable advice, including utility profiling to avoid conflicts with underground utilities, conducting early geotechnical due diligence to identify obstacles, and producing clear, detailed construction documents to reduce errors and change orders.
When it comes to construction for land development projects, there are a variety of factors that could result in snags and delays. The good news is that developers can take action to mitigate construction delays before a project is even designed. The biggest key to staying on track is thorough site civil due diligence.
"Quality construction documents provide clarity and reduce the need for constant revisions. When contractors understand the plans from the start, it minimizes errors and streamlines the construction process."
At Bohler, we design with constructability in mind, which streamlines the bidding and construction process. Sometimes, slowdowns in the field are inescapable, but effective due diligence raises awareness of potential construction challenges and can help minimize delays.
Actionable Tips to Streamline Construction
While some uncertainty below ground is inevitable, most challenges either result from unknown existing utilities or different soils than shown in the geotechnical report.
Here are five actionable tips for mitigating snags once shovels hit the ground based on my experience managing site civil engineering design projects over the past 24 years.
1. Utility Profiling
Between landscaping, water, sanitary utilities, stormwater materials, fiber, gas, electricity and more, designers have a lot to consider. I recommend involving a utility specialist to examine the existing utilities on the site. They can access up-to-date plans from electric and fiber companies, which are more reliable and provide a clear picture of where utilities are located on the site. Underground fiber cables are essential to locate before construction begins because they are hard to find and expensive to fix.
Utility profiling helps identify the depths and intersections of underground utilities, ensuring that crossings are free of conflicts and objects are far enough apart. This critical step helps avoid time-consuming change orders or the need to modify plans on-site.
2. Geotechnical Due Diligence Early On
Geotechnical due diligence is also essential early to clarify other obstacles like groundwater, buried objects, rocks and more. While it may seem expensive, it can help avoid delays and costly adjustments once construction begins. It also helps inform projected costs based on conceptual grading plans, soil considerations and earthwork – which can all affect design.
3. Quality Documentation
Construction documents that are detailed yet easy to understand provide peace of mind for contractors and owners. Buried utilities and other obstacles are presented in multiple ways, allowing for clarity. Contractors can, therefore, consider constructability before they begin, consult plans at any time and project more accurate costs and timelines. Quality construction documents also typically mean contractors don’t need to ask as many questions and submit fewer requests for information (RFIs) or change orders.
For the projects that Bohler is involved in, quality documents lead the way: clear, legible, well-thought-out designs mean that there’s less room for error.
4. In-Person, On-Site Kickoff Meetings
With the most precise possible directions, contractors’ jobs should go much smoother. Kickoff meetings with contractors that are in person and on site are important so that the site civil engineer can go through the construction documents before construction begins.